Jersey Precast – LaGuardia Airport Parking

INFOTRAN provided shop drawing review for the design and fabrication of pre-stress structural members for a parking garage at the central terminal of LaGuardia Airport.

The scope of work included but was not limited to:
• Design and fabrication of precast and pre-stressed structural concrete members for the parking garage.
• Reviewing of shop drawings of the individual concrete members
• Scheduling of concrete pour for fabrication of members as per the erection schedule, tracking the progress of the job using Smart sheet.
• Conducting thorough review of the shop drawings for comments by the Engineer and incorporating all necessary changes for approval, before release for production and assisting the Senior Project Engineer in various daily activities and attending weekly progress meetings.

Project ID#105

Owner

PRIVATE

Location

New York, NY

Status

Design
Schedule Control
Project Management