InfoTran Engineers, P.C. served as a subconsultant perform of the following task.
Preliminary Review of Various Barrier Technology Options: This task included a preliminary review of the roadway flood barrier as proposed by BPCA. The review included advantages and disadvantages of the proposed barrier technology including performance information, where available and identification of other options for consideration if applicable. InfoTran was also involved in the review of only the deployable flood barrier not the permanent barrier, review the structural, mechanical, civil, traffic, and utilities.

Owner

Battery Park City Authority

Location

New York, NY

Unique Attributes

Preliminary Design review
Roadway flood barrier
Structural Inspection